BOSTON KITCHEN UPGRADE/ PROJECT – updates
Updated Scope of work (for contractor)
- Replacement of existing plastic roof with GI roofing
- Installing of ceiling kitchen and office. Installing of wire mesh (kitchen -gap between ceiling and wall, office – between unit 9 and our unit, see image #1 for sample of wire mesh)
- Take out grill (that is connected to mormon wall and kitchen ceiling.)
- Taking out tiles on the sink and cementing (to match counter at wall) (take out whole counter with old sink)
- Installing of Sink and fixing piping (after cemented counter top is installed. tap into downspout. #6)
- Creation of cemented counter at the wall (Mormon side) with hole (provision for LPG hose)
- Tiling of kitchen area (smooth cement finish)
- Dismantle of floor divider in wash room (CR) and cementing
- Fixing of steps on stairs
- If with extra cement, cementing of flooring of inside kitchen (where we dismantled kitchen sink)
- rerouting of water supply from CR through ceiling see image #2.